-
help Learn how to HIGHLIGHT & ADD NOTES
- HOLD LEFT CLICK
- DRAG MOUSE OVER TEXT
- RIGHT CLICK SELECTED TEXT
Land Reclamation
A river delta is a landform that forms from deposition of sediment that is carried by a river as the flow leaves its mouth and enters slower-moving or stagnant water. This often occurs where a river enters an ocean. The river builds them up, the sea wears them down; their outlines are always changing. The changes in China's Pearl River delta, however, are more dramatic than these natural fluctuations. An island called Chek Lap Kok with six kilometres long and a total area of 1248 hectares is being created there. And the civil engineers are as interested in performance as in speed and size. This is a bit of the delta that they want to endure.
Chek Lap Kok was assimilated via land reclamation into the 12.48 square kilometres island for the current Hong Kong International Airport. As the new of Chek Lap Kok rose, however, another new Asian island was sinking back into the sea. This is a 520-hectare island built in Osaka Bay, Japan, that serves as the platform for the new Kansai airport. Chek Lap Kok was built in a different way, and thus hopes to avoid the same sinking fate.
The conventional way to reclaim land is to pile sand rock on to the seabed. When the seabed oozes with mud, this is rather like placing a textbook on a wet sponge: the weight squeezes the water out, causing both water and sponge to settle lower. The settlement is rarely even: different parts sink at different rates. So buildings, pipes, roads and so on tend to buckle and crack. You can engineer around these problems, or you can engineer them out. Kansai took the first approach; Chek Lap Kok is taking the second.
The differences are both political and geological. Kansai was supposed to be built just one kilometre offshore, where the seabed is quite solid. Fishermen protested, and the site was shifted a further five kilometres. That put it in deeper water (around 20 metres) and above a seabed that consisted of 20 metres of soft alluvial silt and mud deposits. Worse, below it was a not-very- firm glacial deposit hundreds of metres thick.
The Kansai builders recognised that settlement was inevitable. Sand was driven into the seabed to strengthen it before the landfill was piled on top, in an attempt to slow the process; but this has not been as effective as had been hoped. To cope with settlement, Kansai's giant terminal is supported on 900 pillars. Each of them can be individually jacked up, allowing wedges to be added underneath. That is meant to keep the building level. But it could be a tricky task.
Conditions are different at Chek Lap Kok. There was some land there to begin with, the original little island of Chek Lap Kok and a smaller outcrop called Lam Chau. Between them, these two outcrops of hard, weathered granite make up a quarter of the new island's surface area. Unfortunately, between the islands there was a layer of soft mud, 27 metres thick in places.
According to Frans Uiterwijk, a Dutchman who is the project's reclamation director, it would have been possible to leave this mud below the reclaimed land, and to deal with the resulting settlement by the Kansai method. But the consortium that won the contract for the island opted for a more aggressive approach. It assembled the world's largest fleet of dredgers, which sucked up 150m cubic metres of clay and mud and dumped it in deeper waters. At the same time, sand was dredged from the waters and piled on top of the layer of stiff clay that the massive dredging had laid bare.
Nor was the sand the only thing used. The original granite island which had hills up to 120 metres high was drilled and blasted into boulders no bigger than two metres in diameter. This provided 70m cubic metres of granite to add to the island's foundations. Because the heap of boulders does not fill the space perfectly, this represents the equivalent of 105m cubic metres of landfill. Most of the rock will become the foundations for the airport's runways and its taxiways. The sand dredged from the waters will also be used to provide a two-metre capping layer over the granite platform. This makes it easier for utilities to dig trenches - granite is unyielding stuff. Most of the terminal buildings will be placed above the site of the existing island. Only a limited amount of pile-driving is needed to support building foundations above softer areas.
The completed island will be six to seven metres above sea level. In all, 350m cubic metres of material will have been moved. And much of it, like the overloads, has to be moved several times before reaching its final resting place. For example, there has to be a motorway capable of carrying 150-tonne dump-trucks; and there has to be a raised area for the 15,000 construction workers. These are temporary; they will be removed when the airport is finished.
The airport, though, is here to stay. To protect it, the new coastline is being bolstered with a formidable twelve kilometres of sea defences. The brunt of a typhoon will be deflected by the neighbouring island of Lantau; the sea walls should guard against the rest. Gentler but more persistent bad weather - the rainfall of the summer monsoon - is also being taken into account. A mat-like material called geotextile is being laid across the island to separate the rock and sand layers. That will stop sand particles from being washed into the rock voids, and so causing further settlement. This island is being built never to be sunk.
Reading Passage Vocabulary
A river delta is a landform that forms from deposition of sediment that is carried by a river as the flow leaves its mouth and enters slower-moving or stagnant water. This often occurs where a river enters an ocean. The river builds them up, the sea wears them down; their outlines are always changing. The changes in China's Pearl River delta, however, are more dramatic than these natural fluctuations. An island called Chek Lap Kok with six kilometres long and a total area of 1248 hectares is being created there. And the civil engineers are as interested in performance as in speed and size. This is a bit of the delta that they want to endure.
Chek Lap Kok was assimilated via land reclamation into the 12.48 square kilometres island for the current Hong Kong International Airport. As the new of Chek Lap Kok rose, however, another new Asian island was sinking back into the sea. This is a 520-hectare island built in Osaka Bay, Japan, that serves as the platform for the new Kansai airport. Chek Lap Kok was built in a different way, and thus hopes to avoid the same sinking fate.
The conventional way to reclaim land is to pile sand rock on to the seabed. When the seabed oozes with mud, this is rather like placing a textbook on a wet sponge: the weight squeezes the water out, causing both water and sponge to settle lower. The settlement is rarely even: different parts sink at different rates. So buildings, pipes, roads and so on tend to buckle and crack. You can engineer around these problems, or you can engineer them out. Kansai took the first approach; Chek Lap Kok is taking the second.
The differences are both political and geological. Kansai was supposed to be built just one kilometre offshore, where the seabed is quite solid. Fishermen protested, and the site was shifted a further five kilometres. That put it in deeper water (around 20 metres) and above a seabed that consisted of 20 metres of soft alluvial silt and mud deposits. Worse, below it was a not-very- firm glacial deposit hundreds of metres thick.
The Kansai builders recognised that settlement was inevitable. Sand was driven into the seabed to strengthen it before the landfill was piled on top, in an attempt to slow the process; but this has not been as effective as had been hoped. To cope with settlement, Kansai's giant terminal is supported on 900 pillars. Each of them can be individually jacked up, allowing wedges to be added underneath. That is meant to keep the building level. But it could be a tricky task.
Conditions are different at Chek Lap Kok. There was some land there to begin with, the original little island of Chek Lap Kok and a smaller outcrop called Lam Chau. Between them, these two outcrops of hard, weathered granite make up a quarter of the new island's surface area. Unfortunately, between the islands there was a layer of soft mud, 27 metres thick in places.
According to Frans Uiterwijk, a Dutchman who is the project's reclamation director, it would have been possible to leave this mud below the reclaimed land, and to deal with the resulting settlement by the Kansai method. But the consortium that won the contract for the island opted for a more aggressive approach. It assembled the world's largest fleet of dredgers, which sucked up 150m cubic metres of clay and mud and dumped it in deeper waters. At the same time, sand was dredged from the waters and piled on top of the layer of stiff clay that the massive dredging had laid bare.
Nor was the sand the only thing used. The original granite island which had hills up to 120 metres high was drilled and blasted into boulders no bigger than two metres in diameter. This provided 70m cubic metres of granite to add to the island's foundations. Because the heap of boulders does not fill the space perfectly, this represents the equivalent of 105m cubic metres of landfill. Most of the rock will become the foundations for the airport's runways and its taxiways. The sand dredged from the waters will also be used to provide a two-metre capping layer over the granite platform. This makes it easier for utilities to dig trenches - granite is unyielding stuff. Most of the terminal buildings will be placed above the site of the existing island. Only a limited amount of pile-driving is needed to support building foundations above softer areas.
The completed island will be six to seven metres above sea level. In all, 350m cubic metres of material will have been moved. And much of it, like the overloads, has to be moved several times before reaching its final resting place. For example, there has to be a motorway capable of carrying 150-tonne dump-trucks; and there has to be a raised area for the 15,000 construction workers. These are temporary; they will be removed when the airport is finished.
The airport, though, is here to stay. To protect it, the new coastline is being bolstered with a formidable twelve kilometres of sea defences. The brunt of a typhoon will be deflected by the neighbouring island of Lantau; the sea walls should guard against the rest. Gentler but more persistent bad weather - the rainfall of the summer monsoon - is also being taken into account. A mat-like material called geotextile is being laid across the island to separate the rock and sand layers. That will stop sand particles from being washed into the rock voids, and so causing further settlement. This island is being built never to be sunk.
IELTS Academic Reading Tips for Success
Tips to improve your reading speed
Keep in mind, having a slow reading speed makes skimming or scanning a reading passage more difficult. The process of quickly skimming through a reading passage for specific keywords or main ideas is a requirement for you to employ successful reading strategies to improve your IELTS reading score. In other words, skimming and scanning are critical skills to ensure you complete all questions in the allotted time frame.
IELTS Reading Strategies
-
Step 1: Read questions first
One of the most common mistakes that candidates make when approaching the reading exam is reading every single word of the passages. Although you can practice for the exam by reading for pleasure, "reading blindly" (reading without any sense of what the questions will ask) will not do you any favors in the exam. Instead, it will hurt your chances for effectively managing your time and getting the best score.
The main reason to read the questions first is because the type of question may determine what you read in the passage or how you read it. For example, some question types will call for the "skimming" technique, while others may call for the "scanning" technique.It is important to answer a set of questions that are of the same question type. You'll need to determine which question type you want to tackle first. A good strategy would be to start with the easier question type and move on to more difficult question types later. The Easiest question types are the ones where you spend less time reading. For example, the Matching Heading question type is an easier one because you only need to find the heading that best describes the main idea of a paragraph. An example of a difficult question type would be Identifying Information. For this question type, you'll need to read each paragraph to find out if each statement is TRUE, FALSE, or NOT GIVEN according to the passage.
Here is a table that lists the difficulty levels for each question type. Use this table as a reference when choosing which question type you want to tackle first.
Difficulty level Question Type Easy Sentence Completion
Short answerMedium Matching Features
Multiple choice
Matching Headings
Summary, Table, Flow-Chart CompletionDifficult Matching Sentence Endings
Matching Information
Identifying Information (TRUE/FALSE/NOT GIVEN)
Identifying Viewer's claims (YES/NO/NOT GIVEN)
-
Step 2: Read for an objective
After you've read the questions for the passage, you will be able to read for an objective. What does this mean? For example, if you come across a question that includes the year "1896", you can make a note of when this year comes up in the text, using it to answer the question later on. There are two reading techniques that will help you stay on track with reading for an objective. The first one, skimming, is best defined as reading fast in order to get the "gist", or general idea, or a passage. With this technique, you are not stopping for any unfamiliar words or looking for specific details. The second technique, scanning, is best defined as reading for specific information. With this technique, you are not reading for the overall gist, but rather, specific information. Notice how each of these techniques has a specific objective in mind. This will help you find information more quickly.
-
Step 3: Take notes
As you're reading for an objective, you should also be making notes on the margins of the passage, placing stars next to key information, or underlining things that you believe will help you answer the various questions. This will make it easier for you to check back when you are asked certain things in the questions. Choose whichever note-taking system is right for you - just make sure you do it!
-
Step 4: Answer wisely
After you've read the questions, read the passage, and have taken any appropriate notes, you you should have located the part of the text where you where you need to read carefully. Then just read carefully and think critically to determine the correct answer.
IELTS Reading Question Types
The IELTS reading test contains many different question types:
Matching Headings | IELTS Reading Lesson: Matching Headings |
Matching Information | IELTS Reading Lesson: Matching Information |
Matching Features | IELTS Reading Lesson: Matching Features |
Summary Completion | IELTS Reading Lesson: Summary Completion |
Identifying Information | IELTS Reading Lesson: Identifying Information |
Identifying Writer's claims | IELTS Reading Lesson: Identifying Writer's claims |
Multiple Choice | IELTS Reading Lesson: Multiple Choice |
Short Answer | IELTS Reading Lesson: Short Answer |
Match Sentence Ending | IELTS Reading Lesson: Match Sentence Ending |
Sentence Completion | IELTS Reading Lesson: Sentence Completion |
Table Completion | IELTS Reading Lesson: Table Completion |